The Ministry of New and Renewable Energy on 2nd February 2022 has issued simplified procedure for the residential consumers to get the rooftop solar plant installed by themselves or through any vendor of their choice under the Rooftop Solar Programme.
The new simplified procedure will be as follows:
- A national portal for registering applications from the beneficiary, approval thereof and tracking progress will be developed. There will be a portal in the similar format at the level of the DISCOMs (Distribution Companies) and both the portal will be linked.
- The household beneficiary, who wishes to install Rooftop Solar (RTS) under the new mechanism will apply on the national portal. The beneficiary will be required to submit necessary information including details of bank account where the subsidy amount will be transferred. At the time of application, the beneficiary will be informed about the complete process and subsidy amount that can be availed for installation of the RTS plant.
- The application will be forwarded online to the concerned DISCOM for issuance of technical feasibility approval within next 15 working days. After the application is transferred to the DISCOM it will also be displayed on the DISCOM portal.
- After obtaining technical feasibility, the beneficiary will install the RTS plant from any vendor of his choice by selecting solar modules fulfilling the conditions of DCR (Domestic Content Requirement) and enlistment under Approved List of Models and Manufacturers (ALMM) and inverters which are certified by J3IS. The beneficiary has to install its plant within a specified period otherwise his application will be cancelled and he has to re-apply for installation of RTS plant.
- Upon installation of RTS plant, the beneficiary will apply for net-metering on the national portal, which will be forwarded online to the concerned DISCOM. The concerned DISCOM will either procure and install the net-meter or it will advise the beneficiary to procure the net-meter as per prescribed specifications and get it tested from the DISCOM authorized lab.
It is expected that the national portal will be developed in about six to eight weeks. Till the national portal comes into operation,the existing procedure for availing subsidy for installation of rooftop solar plant through DISCOMs will continue and will be the only authorized procedure to avail subsidy from MNRE. After the National portal set up, the beneficiary will have the choice of installing RTS availing either of the options.